Antai San Ying is vigorously building a research and pilot-testing base for welding materials at China Iron & Steel Research Institute, paving the way for high-quality development!


 

Project Name: Buildings No. 1, 2, 3, 4, 5, 6, and 7, Phase 1.2 of the Sujiatun Intelligent Equipment Manufacturing Industry Port
 
Structural form: The factory area features a portal steel frame, while the office building area is a three-story frame structure.
 
Enclosure structure:
 
Roofing outer panel: V-470; Insulation layer: 100mm-thick glass wool.
 
Roof inner panel: Uses V-900
 
Wall exterior panel: V-750; Insulation layer: 100mm-thick glass wool.
 
Wall inner panel: Uses V-900
 
Project Overview: Length: 73.2 meters, Width: 55.2 meters, Eave Height: 10.2 meters
 
Project Location: Sujiatun District, Shenyang City

 

Power by : 300.cn Beijing